+ | *1. nov : design layout finished | ||
+ | *8. nov : static html layout presentable | ||
+ | *29. nov : main work done | ||
+ | *3. dec : hard deadline | ||
+ | |||
+ | == Application Structure == | ||
+ | |||
+ | Using MVVM: | ||
+ | |||
+ | = [[File:]] = | ||
= Summary of requirements = | = Summary of requirements = |
Revision as of 13:22, 27 October 2014
Contents
- 1 List of group members
- 2 Project Suggestions
- 3 [[File:]]
- 4 Summary of requirements
- 5 Time schedule
- 6 Milestones:
- 7 How you are dividing tasks within the group
- 8 Screenshots and screen flows
- 9 Documented learning during project
- 10 Suggested improvements to APIs etc
- 11 Link to repository
- 12 Download link to sample web app or Android app
List of group members
- Bård Winther (baardew) baardew@ifi.uio.no
- Henrik Tufte Lien (henriktl) tuftelien@gmail.com
- Jonas Sandnes (jonsandn) jonsandn@ifi.uio.no
- swati sharma (swatis) swatis@ifi.uio.no
Project Suggestions
New Schedule
- 1. nov : design layout finished
- 8. nov : static html layout presentable
- 29. nov : main work done
- 3. dec : hard deadline
Application Structure
Using MVVM:
[[File:]]
Summary of requirements
Time schedule
Milestones:
- Milestone 1: 1st November
Document features and architecture on Wiki
Show understanding of DHIS2 web apps
- Milestone 2: 15th November
First bare-bone version - static HTML
Uploadable as DHIS2 web app
- Milestone 3: 30th November
- Finished, if applicable also with mobile app.
- Final delivery: 8th December
- Presentation: 9th December