Difference between revisions of "Pandapop"
From mn/ifi/inf5750
Anhlv@uio.no (talk | contribs) (→Architecture) (Tag: Visual edit) |
Anhlv@uio.no (talk | contribs) (→Milestone 1: 8th November) (Tag: Visual edit) |
||
Line 31: | Line 31: | ||
==== Milestone 1: 8th November ==== | ==== Milestone 1: 8th November ==== | ||
+ | * Show understanding of DHIS2 web apps | ||
==== Milestone 2: 22th November ==== | ==== Milestone 2: 22th November ==== | ||
+ | * Demo up and running on our own computers | ||
+ | * Show understanding of the Tracker Capture app and its technologies | ||
+ | * First mockup ready | ||
− | ==== Milestone 3: 4th December ==== | + | ==== Milestone 3: 25th November ==== |
+ | * Learn Angular and how to use this within the prosject | ||
+ | |||
+ | ==== Milestone 4: 4th December ==== | ||
+ | * Implement the new feature | ||
+ | * Testing | ||
==== Final delivery: 11th December ==== | ==== Final delivery: 11th December ==== | ||
== Tasks Divided == | == Tasks Divided == | ||
+ | We have not divided any tasks yet as we are still working as a team to understand how we want to implement the new feature to the tracker capture app. | ||
== Link to repository == | == Link to repository == | ||
* git@github.com:lanavu/inf5750.git | * git@github.com:lanavu/inf5750.git |
Revision as of 20:01, 22 November 2015
Contents
Project details
Improving usability in Tracker Capture app
Group members
Saliq Nadeem Dar - saliqnd@ifi.uio.no
Martin Dang - martdan@ifi.uio.no
Inthu Raveendran - inthura@ifi.uio.no
Lana Vu - anhlv@ifi.uio.no
Summary of requirement
To improve the usability in the tracker capture app the previous records should appear for the user when entering new values on a new report. This is only possible for the ANC Visit (2-4+) as the ANC 1st visit will not av have any previous records yet.
The previous records should appear on the same page like shown below.
Architecture
- DHIS2-App
- Javascript - AngularJS/JQuery
- CSS3
- HTML5
Mockups
Time schedule
Milestone 1: 8th November
- Show understanding of DHIS2 web apps
Milestone 2: 22th November
- Demo up and running on our own computers
- Show understanding of the Tracker Capture app and its technologies
- First mockup ready
Milestone 3: 25th November
- Learn Angular and how to use this within the prosject
Milestone 4: 4th December
- Implement the new feature
- Testing
Final delivery: 11th December
Tasks Divided
We have not divided any tasks yet as we are still working as a team to understand how we want to implement the new feature to the tracker capture app.
Link to repository
- git@github.com:lanavu/inf5750.git